Scotland’s largest offshore wind farm has passed another major milestone, that is the successful installation of 19km of onshore cable in each of the three power circuits from the Carnoustie landing to the new substation currently under construction in Tealing, near Dundee.
Seagreen’s onshore project manager Steven Reid said: “This is a huge engineering feat, including the installation of 117 separate cables along the route, involving crossing the East Coast Main Line, the A90 and A92, and minimizing disruption to the Carnoustie and Panmure golf courses.”
“This is a key activity for the Seagreen project in preparation for the first electricity exports this summer, and we are now in the final stages of restoring and replanting the land affected by the cable lines, which will continue until the end of the year.
With the support of our contractors Nexan and Linxon, we are also donating some cable rolls to local schools in Carnoustie, Murroes and Tealing that will be used in each school playground.”
The Carnoustie’s landing project was completed earlier this year, and since then, the project has successfully completed the second of three cable traction at the landing time to support offshore cables to onshore cables.
The Seagreen wind farm is a joint venture between SSE Renewables and Total Energies and is currently under construction about 27 km from the Angus coastline.
Once operational, the site will become Scotland‘s largest and the world’s deepest fixed-bottom offshore wind farm, providing enough clean electricity to about two-thirds of Scotland’s homes.
유럽의 의료 산업은 최근 몇 년 동안 상당한 발전을 이루었습니다., driven by the integration…
로켓의 성공적인 발사에는 상상할 수 있는 가장 복잡한 엔지니어링 업적 중 하나가 포함됩니다.,…
광섬유 케이블은 현대 통신의 중추가 되었습니다., offering high-speed data transmission over…
고전압 구리 케이블은 전력 분배 및 전송에 필수적인 구성 요소입니다.,…
Railroad high voltage lines play a vital role in powering the railway systems that transport…
광섬유 케이블은 현대 통신 네트워크의 중요한 구성 요소입니다., enabling high-speed data transmission over…